The expansion of the C Concourse at Seattle-Tacoma International Airport is taking shape, and passersby can now get a sense of what the completed project will look like as work on the exterior facade and window installation continues.
The $399 million project will expand the existing concourse by some 146,000 square feet via the addition of four new floors above the current structure, at the point where the current C and D concourses meet.
Early work began on the project in summer 2022, with major construction kicking off in 2024. Turner Construction is the general contractor.
Substantial completion is projected for the second quarter of 2026, before the start of FIFA Men’s World Cup tournament events in Seattle.
The Miller Hull Partnership and Woods Bagot have partnered to design the expansion, which will add a host of new amenities in a distinctive biophilic space inspired by the region’s natural beauty.
“Miller Hull has been committed to sustainable design long before it was fashionable or marketable. They…
7-11-2022 | News
The private house occupies a unique position in both the history of architecture and human imagination.…
2-16-2026 | News
By Eric Baldwin The Miller Hull Partnership has earned a Living Building Challenge Petal Certification for the…
5-25-2020 | News
“The time to reassess our built world is now, not after the next catastrophe.” . The…
10-7-2020 | Perspectives
A huge section of the University of Arizona has been revitalized and given new life by Miller Hull…
10-31-2022 | News
Student Success District, University of Arizona Architect: The Miller Hull Partnership LLP and Poster Mirto McDonald Owner: University of Arizona…
4-25-2023 | News